Buildings 800 and 2300 have been officially handed over to Bayley for phase 2 of the Bracken project. Preparation for demolition has begun according to the following schedule:
Building 2300
- 4/22 – 4/27: Abatement
- 4/27 – 5/12: Full Demolition
Building 800
- 4/24 – 4/28: Abatement
- 4/29 – 5/14: Full Demolition
In preparation for the demolition of Building 2300, Wartel will temporarily shut off power to Buildings 2000 and 2100 this Thursday, 4/23, from 5am – 6:30am. This outage is necessary to safely disconnect Building 2300 in preparation for its scheduled demolition.
We appreciate your patience during this necessary prep work.