Hello Campus Community,
Update 1: Roof Work
Our recent roof project got off track due to the ice and the need to do more repairs to the roof at 2900 building. Due to these delays, the 2900 building is still in process and the timeline for 3000, 4000, and 1600 has shifted. Here is the new schedule starting next week.
- 3/21/25
- 2900 roof gravel replacement and perimeter work will be completed by Friday, 3/21. Contractor will be removing their equipment from that area. Parking in front of that building will be open starting Monday, 3/24.
- 3/24/25 – 4/1/25
- 3000 soffit stain work – Contractor will be using a lift and scaffold to apply a stain to the soffit around the building. They will start spraying on the south side starting Tuesday, 3/25. No vehicles can be parked in the motorcycle parking stalls on the north side and the parking stalls on the east side of 3000 when they start to apply the stain. Security will close off the parking in these areas starting Tuesday. Parking should be back open on Monday, 3/31.
- 3/24/25 – 4/4/25
- 4000 skylight replacement – Contractor will remove existing skylight and replace with new. There will be noise and chemical smells during this project. To minimize the impact of dust/sawdust falling within the library, a section inside the 2nd floor will be closed starting Monday, 3/24.
- 4/1/25/25 – 4/8/25
- 1600 PMMA and drain replacement – Contractor will be replacing the roof drainage system. This will require interior and exterior work. There will be slight noise and chemical smell.
Feel free to reach out if you have any questions.
Update 2: Bridge Repair
We will be starting our pedestrian bridge repair project at building 3000 next week. The purpose of this project is to reseal the top deck of the pedestrian bridge, resurface and fill in the cracks on the pedestrian ramp, and repair/seal the concrete underneath the pedestrian bridge. The project schedule will run from 3/24/25 to 6/5/25.
3/24/25-4/4/25 – Contractor will start with the top of pedestrian bridge. The bridge will be closed in sections to allow for access. The Contractor will also be closing the ramp at 3000 to resurface and fill in the cracks. SDS for the sealant will soon follow.
4/21/25 – 5/16/25 – Contractor will be working underneath the 3000 pedestrian bridge to seal/repair the concrete. There will be access to 3000 underneath the bridge.
Feel free to reach out if you have any questions.
Thank you,
Kim Clark
Director of Facilities and Capital Projects